All dispositive motions in the case shall be filed within thirty (30) days after the
scheduled date for the end of all discovery.
APPENDIX A
TIMELINE
Event Deadline
Rule 26(f) Meeting 21 days prior to Rule 16 conference
Filing of Civil Case Management Plan 14 days prior to Rule 16 conference
Rule 16 Conference 120 Days after filing/removal of the action
Patentee Infringement Contentions 14 days after Rule 16 conference
Accused Non-Infringement/ 30 days after service of the disclosure of asserted
Invalidity/Unenforceability Contentions claims and infringement contentions
Exchange of Claim Terms for Construction 60 days after Rule 16 conference
Exchange of Proposed Constructions 21 days after exchange of lists of proposed terms
for construction
Joint Claim Construction Statement 21 days after exchange of proposed construction
Completion of Claim Construction Discovery 30 days after filing of joint statement
Opening Markman Briefs 45 days after filing of joint statement
Opposing Markman Briefs 30 days after opening Markman submissions
Advice of Counsel Disclosure 30 days after claim construction decision
Initial Expert Reports (non-claim construction) 60 days after claim construction decision
Responsive Expert Reports 30 days after service of initial expert disclosure
Completion of All Discovery 120 days after claim construction
Filing of Motions 30 days after close of fact discovery
TIMELINE SUMMARY
Filing of Suit to Full Markman Briefing 297 Days
Claim Construction Decision to Motion Deadline 150 days